Buyer checklist

Before comparing totals, check that every contractor has priced the same work. A quote that leaves out installation labour, testing or equipment setup is not equivalent to a complete proposal.

Last reviewed: . These guides explain costs and project scope, not an ICS price list or an installed estimate. A site assessment and labour quote are needed for a meaningful total.

Give everyone one scope

For cabling, mark each run and identify both ends. For cameras, mark the views and recording needs. For Wi-Fi, identify the users and areas that need service. If the route or equipment choice is still unknown, say so; otherwise each contractor may price a different job.

Separate physical cabling from equipment supply, security setup, wireless design and electrical work. ICS’s confirmed infrastructure services do not establish that it provides every task in a complete camera or Wi-Fi system.

When a quote leaves out required work

Imagine two quotes for the same office cabling job. The first appears cheaper but excludes the patch panel, cable labels and test results. The second includes those items. You cannot compare the totals fairly until the first contractor prices the omissions in writing.

A similar gap occurs when a CCTV proposal lists cameras and a recorder but not the cable paths, mounting, network power, recording setup or labour. For Wi-Fi, an access-point count without radio design or configuration also leaves the scope incomplete.

Approximate comparisons are not final totals. Equipment-only figures, provisional allowances and other incomplete amounts are not installed quotes. The full cost must include required labour, access, testing, any separate trades, applicable tax and recurring services where relevant. Do not assume omitted work is free.

Compare the line items

Write the answer beside each bid
Line item Ask for Resolve before acceptance
Quantity and unit Run count, both ends, category and drawing revision. Does “drop” mean a cable pull or a completed link?
Pathway and access Supports, containment, lift, firestopping, permitted hours and finishing. Which route has been checked, and what could change it?
Equipment Models, capacity, supply, ownership, setup and support. Is this supply only or a commissioned system?
Testing and handover Method, acceptance criteria, labels, reports and failed-link correction. Do both quotes provide the same evidence?
Timing and service continuity Lead times, phases, outage window, cutover and recovery plan. Who approves moving a live connection?
Commercial terms CAD subtotal, HST, validity, payment stages, allowances and exclusions. Is each required item fixed, provisional or unpriced?
Warranty and support Parts/labour coverage, term, exclusions and service process. What is written, and who provides it?
Recurring services Required fees, term, renewals, cancellation and data export. What is the full commitment after installation?

These are questions for each contractor. They are not promises about ICS warranties, certifications, free visits or support policies.

Name a provider for each responsibility

Assign the work before accepting a price
Work Provider to name Required handover
Copper/fiber infrastructure Cabling contractor; confirm ICS scope in the quote. Run schedule, labels and agreed test records.
Cameras and recording Security equipment provider/integrator unless expressly agreed otherwise. Working views, recording/export demonstration and access ownership.
Wireless and network setup IT/wireless provider unless expressly agreed otherwise. Placement/design, configuration, agreed validation and administrator access.
Electrical and building work Responsible electrical/civil/building trades and property manager. Approvals, safe access, completed pathways and required records.
Business decisions Owner/facilities/IT lead. Privacy decisions, outages, acceptance and written changes.

Compare materials and finished work, not just line-item prices

Ask each contractor to state the proposed cable type, connection components, rack or panel hardware, camera or Wi-Fi equipment where relevant, and any substitutions allowed. A low material total may reflect a smaller scope, not a better deal.

Confirm who supplies and installs the equipment, who is responsible for configuring it, which tests are included, and what records you receive. If one quote excludes labour, lifts, panels, patch leads or required specialist work, it cannot be compared directly with an installed quote.

Where materials are listed with prices, treat those as that provider’s dated proposal for a defined quantity, not a market benchmark. Confirm the labour and access scope, applicable taxes and any subscriptions before deciding on a complete project price.

Keep allowances and changes visible

An allowance is a placeholder for an unresolved purchase or task. Record what it covers, how the final amount will be established and who approves it. A contingency is money you hold for uncertainty; it is not automatically a contractor charge. Keep optional improvements outside the required-work subtotal.

Agree how a route change, extra run, failed legacy cable or after-hours request will be priced. The written change should state the added scope, amount, tax and schedule effect before work proceeds. For a larger occupied site, identify who can approve each phase and which services must stay available.

For managed services, compare the whole contract term, required internet or related services, renewal terms and exit costs. The Wi-Fi guide separates those open items from its installation model; the camera guide separates cabling from recording and security setup.

Send this to contractors

  • Site address, drawing revision, numbered endpoints and the result each system must deliver.
  • Existing equipment to reuse, photos of racks/routes, ceiling heights and known access problems.
  • Category or equipment requirements, proposed pathways and responsible IT/security contacts.
  • Permitted hours, deadline, outage limits, landlord approvals and work assigned to other trades.
  • Required labels, tests, reports, training and acceptance conditions.
  • A request for itemized CAD pricing, tax, assumptions, exclusions, recurring fees and written change terms.

A small shop can use a marked sketch and a short scope list. A larger project may need drawings, asset schedules and phased acceptance. The site-survey guide explains what a route review can resolve. Ask whether a visit, design or report is chargeable; ICS’s fee policy is not established here.

Related planning

Prepare your project details

Use the site, equipment and access details from this guide to organize the physical installation scope.

Plan your project

Request a Quote

Planning a cabling, network, Wi-Fi or security-infrastructure project? Share the site and scope you know so far.